Project Assumption Log Template: Add an Owner and a Check Date

Write the assumption as a statement you can check, give it an owner and a check date, and say what will change if it is false. Update the same entry when you get evidence. That is enough to start a usable project assumption log. PMI’s assumptions log example

Jump to the template

Make the entry testable

“Assets on time” gives the reviewer little to check. “The client will send approved homepage assets by Wednesday at noon” gives the owner a receipt to look for and a time to check it.

Record why the plan relies on the assumption. In this launch, the designer needs approved assets ahead of Friday’s build. The person responsible for confirming receipt can differ from the person who sends the files.

Use a check date that still leaves time to react. Checking on Friday would tell you what went wrong after the alternative slot had already passed.

Follow A-07 from open to disproved

Priya owns A-07. On Wednesday at noon she checks the client’s thread. The files have arrived but are marked “draft,” so they fail the approval condition. She records the message and the time in the note.

TodoNote · A-07 · Confirm approved assets · The assumption note keeps the evidence, the owner, and the fallback in view.
The assumption note keeps the evidence, the owner, and the fallback in view.

She changes the status to disproved and opens the fallback artwork task. The log keeps the original wording and the evidence that prompted the change. Anyone reading it later can see why the Friday build now uses fallback assets.

Use an issue log for the problem once it has occurred, or a risk register for an uncertain event that might affect the plan. Link the records when the same facts inform both.

Copy a one-entry template

Create one entry for each belief that affects a decision. A stable ID helps when a schedule or issue refers back to it.

ID and assumption:
Plan or decision that depends on it:
Verification owner and check date:
What counts as confirmation:
Status (open, confirmed, or disproved):
Evidence and date checked:
Action if it is disproved:
Plan your next step in TodoNote

If the check date passes with no evidence, keep the entry open and record the new decision about waiting or using the fallback. Absence of a reply has a different meaning from confirmed approval.

See the project risk register template to track a threat that remains uncertain.